previous Report (§414), public housing supply was included mainly as part of the programme
to build 10,000 houses and develop 50,000 building plots begun in 2009. Although the
execution of this project recorded all types of challenges including financial, land and
operational challenges, some 2,475 houses were available at the end of 2017; that is, 1,300 in
Yaounde (Olembe) and 1,175 in Douala (Mbanga-Bakoko). As part of the programme, out of
the 1,800 houses to be built through cooperation with China232, 1,520 were completed at the
end of 2017 in 6 towns233.
381- In addition, as part of the Three-year Emergency Plan to Accelerate Economic Growth
(PLANUT)234, the construction of 100 houses in every Regional Headquarters excluding
Yaounde and Douala is underway.
382- A Project dubbed “Cité des Cinquantenaires” was also launched. At the end of 2017, the
construction of 530 houses out of the 1,050 earmarked for Douala had kicked off and the
construction of 500 houses out of the 900 planned for Yaounde was ongoing235.
383- In a bid to address the financial challenge that sometimes had a negative impact on the
progress of public programmes to promote real estate, land bases allocated to low-cost
housing were earmarked for land reserves defined by the State (See § 161 above).
384- With regard to private housing supply, in 2016, real estate promoters built 1,200 houses
and developed 15,000 plots.
B: Development of Building Plots
385- Development of building plots is one the actions carried out by the State to enhance the
livability of houses. In this regard, in 2014, Government executed Phase I of the development
of 1,104 building plots in Yaounde (Olembe and Mbalngong) and in Douala (Bwang Bakoko
I and II) and the construction of low-cost houses at Olembe and Mbanga Bakoko by
MAETUR.
386- Development works were carried out at the Ekoko II site (16 ha) with a view to resettling
expropriated people for public utility under the Yaounde-Nsimalen Superhighway
Programme. Works on the resettlement site of Ngolzock (100 ha) were launched in 2017.
387- In addition, vast new areas will be acquired soon, and they are in Lobo (400 ha),
Mbankomo (200 ha) and Massoumbou (500 ha).
388- As part of the Constitution of Land Reserves Project, development works spread over
739,360 ha and concern Ndian, Faro and Deo, Mbere, and Djerem Divisions. At the end of
2017, more than 60% of works were executed on each of the sites.
§2: Actions to enhance the Standard of Living
389- Enhancement of the standard of living was carried out within the framework of
renovation and urban restructuring operations.
A: Enhancement of the Urban Environment
390- As part of renovation and restructuring of quarters with precarious habitats, projects
were carried out with the aim of increasing access of the people of the said quarters to basic
infrastructure and services. The projects include the Urban Sectors Development and Water
232
The amount of this section of the Programme stood at CFAF33,500,000,000 (About 51,145,038.16 Euros)
including Cameroon’s contribution of more than CFAF5,000,000,000 (About 7,633,587.78 Euros).
233
Yaounde, Douala, Limbe, Bafoussam, Bamenda and Sangmelima.
234
Progress rate stands as follows: Ebolowa 80%, Bertoua 25%, Buea 29%, Bafoussam 20%, Ngaoundere 30%,
Garoua 27%, Maroua 25% and Bamenda 6.1%.